Exterior Home Maintenance Project

 

Scope of Work

  • Exterior Repairs
    • Lower Roof Repairs
    • Gutter Repairs
    • Post & Footing Repairs
    • Fascia, Eaves, & Trim Repair
  • Exterior Painting
In conjunction with these planned exterior improvements, Hickam Communities will also inspect, assess, and perform work in accordance with Environmental Protection Agency ("EPA") guidelines. Hickam Communities (“HC”) employs a Lead-Based Paint Management Program on selected homes built before 1978. 
 
 

What to Expect

Written notice will be provided to impacted residents two weeks prior to work beginning. Additionally, 48-hours prior to work commencing, residents will receive an in-person visit* by their community management office, along with a member of the construction project team, to go over the scheduled work and answer any questions. *In-person visit subject to COVID-19 social distancing limitations.
 
Our Commitment:
  1. Work is being performed by a qualified third-party company with oversight by a HC project management team.
  2. Resident health is not a risk while work is being performed, as confirmed by third-party health consultants.
  3. The Community Manager will be available to answer questions via phone and email. This information will be provided in the 2-week and 48-hour notice. 
 

Status Update

Project Start: August 2, 2021*
  • Total homes affected by this project: 109
  • Work Hours:
    • 8:00am-4:00pm, Monday-Friday*
  • We will need your assistance and ask that you move your vehicle(s) or items stored outside in the carport, front porch and back porch to protect your property and ensure work can be completed safely. This will also be communicated to you at the 2-week and 48-hour notification prior to work commencing.

Current Homes in Progress

302-A SIGNER BOULEVARD Friday, October 1, 2021 Friday, October 29, 2021
302-B SIGNER BOULEVARD Friday, October 1, 2021 Friday, October 29, 2021
302-C SIGNER BOULEVARD Friday, October 1, 2021 Friday, October 29, 2021
302-D SIGNER BOULEVARD Friday, October 1, 2021 Friday, October 29, 2021
302-E SIGNER BOULEVARD Friday, October 1, 2021 Friday, October 29, 2021
302-F SIGNER BOULEVARD Friday, October 1, 2021 Friday, October 29, 2021
212-A 15TH STREET Tuesday, October 12, 2021 Friday, November 12, 2021
212-B 15TH STREET Tuesday, October 12, 2021 Friday, November 12, 2021
212-C 15TH STREET Tuesday, October 12, 2021 Friday, November 12, 2021
212-D 15TH STREET Tuesday, October 12, 2021 Friday, November 12, 2021
212-E 15TH STREET Tuesday, October 12, 2021 Friday, November 12, 2021
212-F 15TH STREET Tuesday, October 12, 2021 Friday, November 12, 2021
212-G 15TH STREET Tuesday, October 12, 2021 Friday, November 12, 2021
212-H 15TH STREET Tuesday, October 12, 2021 Friday, November 12, 2021
212-I 15TH STREET Tuesday, October 12, 2021 Friday, November 12, 2021

*Work will be completed as scheduled, barring unfavorable weather conditions. In the event of inclement weather or other latent conditions, we will be sure to provide updates to the original timeline.


Additional Resources

  • Exterior Home Repair FAQ
  • Click here to determine if your home is part of this exterior repair project. Homes within the red outline are included. Map subject to change as work progresses.